Slide 05 · Implementation Timeline
5 Phases · 12–14 Weeks
Structured Delivery
Total Duration
12–14
weeks
Phases
5
sequential
01
Requirement Study
1–2 weeks
02
System Design
2–3 weeks
03
Development & Configuration
3–4 weeks
04
Pilot Deployment
2–3 weeks
05
Full Rollout
2–3 weeks
Phase 01
1–2 weeks
Requirement Study
01
Key Deliverables
Site visit & process walkthrough
BOM & master data collection
Station-level requirements
Hardware sizing finalization
Stakeholder alignment
Dependencies:
Client availability, plant access
Timeline Overview
01
Requirement Study
1–2 weeks
02
System Design
2–3 weeks
03
Development & Configuration
3–4 weeks
04
Pilot Deployment
2–3 weeks
05
Full Rollout
2–3 weeks
Week 0
Week 4
Week 8
Week 12–14
Key Assumptions & Dependencies
BOM & master data provided on time by MHI
Hardware procurement & installation by MHI team
Network setup (static IPs, LAN) ready before pilot
Operator availability for training sessions
ERP access credentials shared before Phase 3