Df-OSMHI Traceability Proposal
Slide 05 · Implementation Timeline

5 Phases · 12–14 Weeks
Structured Delivery

Total Duration
12–14
weeks
Phases
5
sequential
Phase 011–2 weeks

Requirement Study

01
Key Deliverables
Site visit & process walkthrough
BOM & master data collection
Station-level requirements
Hardware sizing finalization
Stakeholder alignment
Dependencies: Client availability, plant access
Timeline Overview
01
Requirement Study
1–2 weeks
02
System Design
2–3 weeks
03
Development & Configuration
3–4 weeks
04
Pilot Deployment
2–3 weeks
05
Full Rollout
2–3 weeks
Week 0Week 4Week 8Week 12–14
Key Assumptions & Dependencies
BOM & master data provided on time by MHIHardware procurement & installation by MHI teamNetwork setup (static IPs, LAN) ready before pilotOperator availability for training sessionsERP access credentials shared before Phase 3